10 year maintenance plan in WA, explained for councils of owners
A 10 year maintenance plan is a written forecast of the major work a strata scheme's common property will need over the next ten years, what it is likely to cost, and how the reserve fund will pay for it. In Western Australia every designated strata company must have one, which in most cases means a scheme of 10 or more lots, and the plan must be revised at least once in each five years.
By Cameron Facilities, Mount Lawley, Perth WA. Published 19 November 2026.
The 10 year plan came in with the strata reforms that took effect on 1 May 2020, under the Strata Titles Amendment Act 2018. For many councils it was the first time anyone had to look ten years ahead and put a number on the roof, the lifts and the repaint. This guide explains what the law requires, what a useful plan looks like and how it ties to the levies owners pay.
Who must have a 10 year plan
Section 100 of the Strata Titles Act 1985 (WA)(opens in a new tab) sets the rule. A designated strata company must establish a reserve fund and must ensure there is a 10 year plan (section 100(2) and (2A)). A designated strata company is a strata company for a scheme with 10 or more lots, or one included by the regulations (section 100(7)).
The Strata Titles (General) Regulations 2019(opens in a new tab) add schemes below 10 lots where the replacement cost of the scheme buildings is more than $5 million, and survey strata schemes where the improvements on the common property would cost more than $5 million to replace (regulation 79). Landgate's WA Strata Living Guide(opens in a new tab) explains the same rule for owners.
The requirement started on 1 May 2020. Strata companies that already existed then had until their first annual general meeting held more than 12 months after that date to present their first plan, and the plan is presented at the annual general meeting (regulations 77 and 179).
Smaller schemes are not required to keep a reserve fund, but the Act allows any strata company to set one up (section 100(2)). Many small schemes find a simple plan worth having for the same reason large ones do: the big items arrive whether or not anyone planned for them.
What the plan must contain
Section 100(2A)(a) says the plan sets out the common property and the strata company's personal property anticipated to need maintenance, repair, renewal or replacement, other than of a routine nature, the estimated costs, and anything else the regulations require. Regulation 77 lists what must be included:
- The strata company's name and the scheme address
- The name and address of the person who prepared the plan
- Where the strata company engages someone to prepare it, the qualifications, if any, of each individual involved
- The period the plan covers
- The list of items covered
- A condition report
- The method used to estimate the costs, including any assumptions
- A plan or recommendation for funding
Regulation 77 also gives examples of items a plan can cover, from roofs, gutters, walls and windows to lifts, fire services, air conditioning, hot water, pumps, backflow devices, car stackers, roof access safety equipment and disability access. For each item the condition report can include the install date, present condition, when it was last inspected, the work anticipated, the estimated date and cost, and the expected life once the work is done.
Reserve fund or administrative fund
The plan only covers work that is not routine. Section 100(2)(a) describes the reserve fund as a fund to meet contingent expenses, other than those of a routine nature, and other major expenses likely to arise in the future. Routine costs stay in the administrative fund. Landgate gives these examples:
| Reserve fund | Administrative fund |
|---|---|
| Roof repairs | Cleaning |
| Replacement of lifts | Gardening |
| Repainting of walls | Small maintenance jobs |
| Changes to building structure | Insurance and utility bills for common property |
| Unexpected expenses not covered by building insurance | Administrative costs and strata management contract fees |
Keeping routine servicing out of the plan matters. If the annual fire service or the lift maintenance contract is also counted in the plan, owners pay for it twice in their levies.
How a good plan is built
A plan is only as good as the information behind it. The most useful plans are built on the building itself, not on standard figures.
Documents first
The strata plan, by-laws, recent minutes, the earlier plan, the list of works completed since, service contracts and the fire, lift and anchor records.
Site walk
Every element photographed and rated, with the council member who knows the history asked what has already been done.
Costs with a basis
Each cost shows where it came from: a quote, an invoice, a contractor's written advice, a published Perth rate, or an allowance clearly marked to be replaced by a quote.
Forecast
Year by year, in today's dollars and escalated, with any contingency shown on its own line rather than buried in every item.
Funding
A recommended reserve levy each year that keeps the fund above nil, or above a minimum balance the council sets, starting from the actual reserve balance.
The five year review
The plan must be revised at least once in each five years, and when it is revised it is extended to cover the ten years following the revision (section 100(2A)(b)). A review is not a fresh start. It should take each item in the earlier plan and record what happened to it: completed, with the invoice or certificate; still outstanding; or pushed out because the condition is better than expected. New items are added, costs are brought to current prices and the levy is recalculated from the current balance.
How the plan connects to the budget and levies
A strata company must prepare a budget each financial year for its annual general meeting, and the budget must take the 10 year plan into account (section 102, as Landgate explains in the WA Strata Living Guide(opens in a new tab)). Contributions to the reserve fund are levied in proportion to unit entitlements (section 100(2)(c)). Where a budget provides for improvements or alterations to common property, other than sustainability infrastructure, costing more than the number of lots multiplied by $500, owners must be given the information and the budget must be approved by special resolution (section 102(5) and regulation 80).
That is why the funding recommendation matters most to owners. It tells them what they will pay, and it should show the current levy beside the recommended one.
Common problems in 10 year plans
These are the problems we look for when we review an existing plan:
- Costs taken from interstate or standard samples rather than Perth quotes or the building's own invoices
- Work the council has already completed carried forward as if it were still due
- Items priced for the wrong material, such as a timber fence that is actually aluminium
- Routine contracted servicing counted again as a reserve item
- A contingency added on top of every line, including quoted ones
- An opening balance of zero standing in for a figure nobody supplied, which drives the levy up
- A plan that has never been checked against what the reserve fund has actually spent
Checklist: what to have ready
Gather these before the plan or review starts. It saves a second site visit and makes the costs more accurate.
- The last 10 year plan and any building inspection reports
- A list of works completed since the last plan, with invoices or certificates
- Current service contracts and the latest reports for fire services, lifts, car park doors, pumps, emergency lighting and roof anchors
- The fire logbook and the fire panel make, model and install year
- Any contractor advice on remaining life, and any painting quotes
- The latest AGM minutes, the reserve fund balance and its date, and the current levies
- The financial year the strata company uses
- Anything the council knows has been fixed, upgraded or replaced
Need a plan or a five year review?
We prepare new 10 year plans for Perth strata schemes and carry out five year reviews, following regulation 77 item by item, with every cost showing its source. Already have a plan? Our Reserve Fund Health Check reviews it against what the fund holds and has spent. See 10 year maintenance plans in Perth.
Sources
- Strata Titles Act 1985 (WA), Western Australian Legislation(opens in a new tab)
- Strata Titles (General) Regulations 2019 (WA), Western Australian Legislation(opens in a new tab)
- Landgate, WA Strata Living Guide (November 2023)(opens in a new tab)
General information about Western Australian law and practice, current at 19 November 2026. For advice on your own scheme, check the current legislation or speak with a lawyer.
10 year maintenance plans: common questions
Is a 10 year maintenance plan mandatory in WA?
Yes, for a designated strata company: a scheme with 10 or more lots, or a smaller scheme whose buildings would cost more than $5 million to replace. The requirement came in with the strata reforms on 1 May 2020, and existing schemes had until their first annual general meeting more than 12 months after that date to present their first plan.
How often does the plan have to be reviewed?
At least once in each five years. When it is revised, the plan is extended to cover the ten years following the revision, under section 100(2A)(b) of the Strata Titles Act.
Who can prepare a 10 year plan?
The regulations do not name a profession. They require the plan to state who prepared it and, where the strata company engages someone, the qualifications, if any, of each person involved, so the council can judge the work. Choose someone who inspects the building in person and shows the source of every cost.
Does the council have to follow the plan exactly?
The plan is a forecast, not an order. The budget must take it into account, and the strata company decides each year what work to approve and what to levy. A good plan makes those decisions easier to explain to owners.
Is routine maintenance part of the 10 year plan?
No. The plan covers work other than of a routine nature. Cleaning, gardening, small repairs and contracted servicing belong in the administrative fund budget.
What if our scheme has fewer than 10 lots?
Unless the buildings would cost more than $5 million to replace, a reserve fund and plan are optional. Many small schemes still keep one so a roof or repaint does not become a special levy.